summing cost accounts in P6.
I have assigned cost accounts to resources, eg: concrete resource to concrete account, steel resource to steel account, etc.
now, after entering actuals for resources, can I put these actuals in the corresponding cost account, & then sum all the actuals for the same cost account?
eg: we have activity a,b,c, & the three of them have concrete resource associated with concrete cost account.
now, activity a has 30$ actuals of concrete resource, activity b has 50 $ actuals, now can I put the actuals form a & b ( 30+50 = 80) in the cost account?
in Primavera by  
retagged by

Please log in or register to answer this question.

Related questions

0 votes
0 answers 82 views
0 votes
1 answer 114 views
114 views asked Aug 11, 2015 in Primavera by mfby2k  
0 votes
0 answers 52 views
52 views asked Jul 29, 2015 in Primavera by mfby2k  
0 votes
0 answers 68 views
0 votes
1 answer 453 views
...