I'm working with a Supt who schedules in Activity Network not Gantt. P6 is changing the physical location of the task according to logical relationships. Is it possible to turn this function off?
in Primavera by  
retagged by

1 Answer

0 votes
Muhammad Qasim Shinwari • That will be so much difficult and boring to use Activity Network ! Any how, arrange them manually and then go to View>Activity Network>Save Network Positions. Then in the similar way you can open the activity network positions. But be advised, in my case, sometimes even this do no not work !