In P6, while i input the activities First 2 activities ok to order but after 3dr activity input and activity type to change to start Milestone then activity line is changed. how can i change this? thanks, Don
in Primavera by  
retagged by

1 Answer

0 votes
What you mean by activity line?? If you mean ORDER then you can sort it using ORGANIZE tool using the respective toolbar.