i have a question , there is a project it has been planned for some dates say that as baseline one. and after some duration of the progress the project has been rescheduled by keeping actuals upto data date same and new planned dates is continued from the data date. so now it became our baseline two. now i have to see on the screen base line one (start, finish dates)base line two( start, finish dates) and (actual start and actual finish) can you give me procedure for this in P3 and P6
in Primavera by  
retagged by

1 Answer

0 votes
Yes, the procedure is simple. As you have already defined 2 baselines (Let me say one is primary and other is secondary baseline). Now right click at bars area and click on bars and make sure that the said baselines( primary and secondary) and actual bars are checked in VISIBLE chekboxes.